The new process yielded many benefits, such as reducing the number of machines and workers required. There was also a significant drop in the noise and dust levels on site. The most important thing is that with this improved process, we have managed to increase productivity by 300%. We also received funding assistance from the Productivity Improvement Project (PIP) Scheme, which helped us to defray costs.
We wil continue to place a strong emphasis on efficient and effective site planning and to provide training opportunities for our staff in this area. We also intend to proliferate the use of the new pile head removal method for al our future projects. We may even set up productivity groups within each project team to improve site processes.